Manufacturing Expansion and R&D Area Renovation
TAI was tasked with the phased expansion of a 20,000 SF existing office space into a GMP manufacturing facility in Columbia, MD. The work included
Pharmaceutical | Biotech | Life Sciences
TAI was tasked with the phased expansion of a 20,000 SF existing office space into a GMP manufacturing facility in Columbia, MD. The work included
TAI worked as the architectural and MEP engineering firm for this project and provided the construction documents in a manner conducive to phased compartmentalized construction,
TAI provided mechanical/plumbing engineering, electrical engineering, process engineering, and commissioning for both new R&D and manufacturing facilities in Gaithersburg, MD (160,000 SF) and San Jose,
TAI provided mechanical HVAC, plumbing, electrical, process and fire protection engineering to provide utility code compliant design of ISO Class 5, 7, and 8 cleanrooms,
The Client expanded its facility to include additional floors at their existing manufacturing and administrative offices areas located in Rockville, MD. TAI provided the mechanical,
TAI installed new compressed air service and electric distribution; fixed exterior/interior walls with (FRP/paint/cove), installed new personnel and material entry doors and new flooring and
TAI performed calibration and testing for all field instrumentation and control loops associated with the plant expansion, including all NIST Calibration Standards, calibration consumables, project
The Client utilized its Maryland campus as a mixed use production facility. To continue meeting the rising demand for its products, the Client needed a
TAI partnered with the Client to upgrade and expand the LAL manufacturing area at their biotechnology facility in Walkersville, Maryland. TAI provided engineering, procurement and
TAI provided engineering, procurement and construction for upgrading the process waste system at Client’s facility located in Frederick, MD. The Client decided to replace two