Client: Distilled Spirits Production Facility

The purpose of this project was to install a new product storage and processing system at the plant. The full scope of work included fabricating a new 100,000 gallon tank on-site, building the tank foundation and containment structure, installing tank ancillary equipment and rail car receiving capability, and constructing a new in-line blending / chilling / filtering system.  Operations associated with the new installation were fully automated.  This continuous in-line blending system represented a paradigm shift for the plant, as previous operations were performed in a batch mode.

TAI supported the client on this project from concept to start-up.  Services provided included initial project scoping/feasibility study, preliminary engineering/cost estimating, and detailed engineering.  This project was performed on a design-build basis, and TAI was also responsible for installation, commissioning, and start-up of the new system.

Project Notes: